Fiscal Year 2025 – Completed Land Use Cases

  • 71 total land use entitlement cases completed, including rezonings, proffer amendments, and special use permits
  • Average completion time (all cases): ~13.88 months
  • Average completion time (Rezonings): ~13.45 months
  • Average completion time (Special Use Permits): ~14.1 months
  • Percentage of Cases on the PC Expedited Agenda: 58%
  • Percentage of Cases on the BOCS Consolidated Agenda: 81.6%
  • Number of Pre-Application meetings: 80 cases

Most cases were completed within reasonable timeframes given application complexity and scope of the Application.

Square feet of non-residential: 2.6 Million

Number of residential units approved: 2,742 units

Outlier Context:
Three cases within the FY 2025 dataset represent clear outliers due to prolonged applicant inactivity and extended periods on hold. These cases skew overall averages upward by several months and are not representative of typical processing timelines.